FRP quality inspection in China: RFQ-to-shipment checklist

FRP inspection works when requirements are converted into measurable hold points before production. A final visual check cannot recover an incorrect resin, fiber architecture, cure, laminate sequence or certificate scope. Use this checklist from RFQ through pre-shipment release.

Technical sourcing referenceUpdated 2026-08-01
Before PO
Close technical deviations
Before production
Approve materials + plan
During production
Witness critical process
Before shipment
Release against evidence
QUICK COMPARISON

Decision matrix

StageInspectEvidenceRelease question
Supplier qualificationLegal site, process, equipment, quality systemAudit, scope, organization and subcontract mapCan this site make and control the offered product?
Material receiptResin, reinforcement, additives, insertsCOA, lot IDs, storage and shelf lifeDo inputs match the approved construction?
First articleDimensions, laminate, surface, fit and functionFAI report, sample, photos and test resultsIs the approved baseline reproducible?
In processMix/cure, fiber placement, temperature, pressure, toolingTravelers, logs, witness pointsAre critical parameters within limits?
Final inspectionQuantity, dimensions, defects, performance, markingInspection report and NCR closureDoes the lot meet every acceptance criterion?
ShipmentPacking, labels, documents and load planPacking list, crate photos, release noteWill accepted product arrive traceably and undamaged?

A practical inspection sequence; project risk sets sample sizes and hold points.

Write acceptance criteria before placing the order

The purchase package should identify drawings and revisions, product construction, standards, dimensions/tolerances, appearance limits, performance, test frequency, sampling, documentation, traceability, packaging and deviation control. Terms such as 'good quality' or 'standard tolerance' cannot be inspected consistently.

Use defect photographs or a visual acceptance standard for pits, blisters, dry fiber, exposed reinforcement, cracks, chips, resin-rich areas, print-through, color and finish. Separate cosmetic limits from structural reject conditions.

Control the process characteristics that final inspection cannot see

Critical controls depend on process: resin formulation and gel/cure for molding; pulling speed, die temperature and fiber placement for pultrusion; winding angle and liner for pipe; charge weight, mold temperature and cure for SMC/BMC. Record the parameters that link raw-material lots to finished batches.

If work is subcontracted, identify the site and inspection responsibility. A supplier quality certificate does not automatically cover a different molding, machining or testing location.

Release the shipment from one evidence index

Create a document index with PO/drawing revision, approved deviations, incoming certificates, traveler/lot records, first article, dimensional report, test results, nonconformance closure, packing list and shipment photographs. Each item should identify the production lot.

  • Verify certificate issuer, site, scope, revision and validity
  • Match tested specimen, thickness and orientation to the supplied product
  • Define retest, concession and rejection authority before inspection
  • Do not release cargo with open critical nonconformances
BUYER FAQ

What should an FRP pre-shipment inspection cover?

It should cover identity/quantity, drawing revision, dimensions, visual defects, required batch tests, marking, traceability, documents and packaging. The exact sample size and tests come from the purchase inspection plan.

Can a final inspection detect the wrong resin or fiber architecture?

Not reliably. Those characteristics require material traceability, process records and sometimes targeted laboratory methods. Control them at incoming-material and production hold points.

Do ISO 9001 certificates prove the FRP product complies?

No. ISO 9001 addresses the quality management system and its certified scope. Product compliance needs product-specific specifications, test evidence and inspection records for the supplied lot.

Primary technical references

References support screening and terminology. Use the applicable paid standard, governing design code and product-specific evidence for final engineering decisions.